The Risk Management of the Bogor-Sukabumi Cross-Rail Dual-Track Construction Project on Time Control
1129 Interdisciplinary Social Studies, 1(8), May 2022
system has various advantages over other land transportation systems including mass
transportation, fast, energy-saving, effective and efficient transportation.
The development of the double track railway between Bogor-Sukabumi was carried out to
increase service capacity and facilitate train travel by making the railway road double.
Development of railway facilities and infrastructure, especially in areas with dense
transportation volumes. The construction of the existing line construction Between Batutulis -
Ciomas between Bogor - Sukabumi is part of the Railway Development program between
Bogor - Sukabumi which was launched as a form of government responsibility for the needs
of passenger and freight transportation to ensure a safe and timely train journey.
Through Law number 23 of 2007 concerning Railways, it is explained that railways as a
mode of transportation in the national transportation system have the characteristics of mass
transportation and certain advantages, cannot be separated from other modes of transportation,
the potential requires development and improvement of its function for regional liaisons, both
national and international, to support, urge, and drive national development to improve the
welfare of the people. In relation to the implementation of the development of the national
transportation network and the National Railway Master Plan, the Directorate General of
Railways has a planning for the construction of a railway double track in Bogor-Sukabumi with
a total length plan of ± 57,215 km.
The Construction Construction Process of the Existing Line Construction Between
Batutulis - Ciomas Lintas Bogor - Sukabumi is carried out with the multiyears contract
mechanism financed by State Sharia Securities (SBSN) for the 2019-2022 fiscal year. To
support the purpose of implementation, the railway is in accordance with the mandate of law
number 23 of 2007 concerning Railways, to reconstitute the implementation of national
railways as a whole. The arrangement for the implementation of railways is stated in the
National Railway Master Plan (RIPNAS) issued by the Directorate General of Railways of the
Ministry of Transportation in 2011. RIPNAS which is the basis and guidelines that underlie all
policies in the management and operation of national railways.
Each stage of the project cannot be separated from the risks and uncertainties that can
occur and affect both in terms of quality and quantity. The construction of the Double Railway
J ulur can occur delays from the contract time limit, if the provider does notanticipate the risks
that may occur and good implementation methods to minimize the risks that can occur.
Theimplementation of risk management is very important to do to reduce the occurrence of
risks in the implementation.
In the implementation of work, unmanaged risks can have an impact on not achieving the
targets of the completion plan according to the planned time. Therefore, this study aims to find
out how to identify the dominant risk of time delays in the implementation of the Bogor-
Sukabumi Cross Railway Double Track Construction and its handling strategies. In addition,
this research is also expected to meet the research gap from previous studies as stated in the
following table.