Financial risk analysis of Public-Private Partnership (PPP) projects case study on Pandaan - Malang Toll Road

Authors

  • Farid Arif Adi Nugroho Universitas Brawijaya
  • Rosid Rosid Universitas Brawijaya
  • Muhammad Tojibussabirin Universitas Brawijaya

DOI:

https://doi.org/10.55324/iss.v3i4.715

Keywords:

financial risk analysis, government cooperation projects, Pandaan - Malang Toll Road

Abstract

This study aims to analyze the financial risks faced by the Pandaan-Malang Toll Road PPP (Public-Private Partnership) project in Indonesia. Data collection techniques include semi-structured in-depth interviews with parties related to the PPP project, including the Directorate General of Infrastructure Financing, the Tolling Road Management Agency (government), and Business Entities (PT Jasamarga Pandaan Malang). The collected data will be analyzed to determine the financial risk factors faced by PPP projects and the financial controls carried out to overcome financial risks in PPP. The results show that the risk of errors in forecasting in the calculation of demand, cost, and revenue projections is a risk that almost often occurs. The Government emphasizes the importance of optimizing the role of PII (Persero) or Indonesia Infrastructure Guarantee Fund (IIGF) as an Infrastructure Guarantee Business Entity (BUPI) to ensure financial sustainability and minimize the impact of sudden shocks on the State Budget due to the provision of Government Guarantees for cooperation projects. This study provides insights or frameworks that can be applied to similar projects, helping to improve risk assessment and decision-making processes in future infrastructure developments.

References

Akomea-Frimpong, I., Jin, X., & Osei-Kyei, R. (2022). Criticality analysis of financial risks of public-private partnership projects in a Sub-Saharan African country. IOP Conference Series: Earth and Environmental Science, 1101(5). https://doi.org/10.1088/1755-1315/1101/5/052026

Alada?, H., & I?ik, Z. (2017). Role of Financial Risks in BOT Megatransportation Projects in Developing Countries. Journal of Management in Engineering, 33(4). https://doi.org/10.1061/(asce)me.1943-5479.0000527

Alonso-Conde, A. B., Brown, C., & Rojo-Suarez, J. (2007). Public private partnerships: Incentives, risk transfer and real options. Review of Financial Economics, 16(4). https://doi.org/10.1016/j.rfe.2007.03.002

Aswanto, A., & Wibowo, A. (2022). Eksplorasi Interdependensi Faktor - Faktor Risiko pada Proyek KPBU Jalan Tol menggunakan Intrerpretive Structural Modeling. Jurnal Teknik Sipil, 29(3). https://doi.org/10.5614/jts.2022.29.3.11

Bing, L., Akintoye, A., Edwards, P. J., & Hardcastle, C. (2005). The allocation of risk in PPP/PFI construction projects in the UK. International Journal of Project Management, 23(1). https://doi.org/10.1016/j.ijproman.2004.04.006

Fernandes, C., Oliveira Cruz, C., & Moura, F. (2019). Ex post evaluation of PPP government-led renegotiations: Impacts on the financing of road infrastructure. Engineering Economist, 64(2). https://doi.org/10.1080/0013791X.2018.1559384

Flyvbjerg, B., Skamris Holm, M. K., & Buhl, S. L. (2005). How (In)accurate are demand forecasts in public works projects?: The case of transportation. Journal of the American Planning Association, 71(2). https://doi.org/10.1080/01944360508976688

Frimpong, Y., Oluwoye, J., & Crawford, L. (2003). Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study. International Journal of Project Management, 21(5). https://doi.org/10.1016/S0263-7863(02)00055-8

Grimsey, D., & Lewis, M. K. (2002). Evaluating the risks of public private partnerships for infrastructure projects. International Journal of Project Management, 20(2). https://doi.org/10.1016/S0263-7863(00)00040-5

Gyadu-Asiedu, W. (2009). Assessing construction project performance in Ghana: Modelling practitioners and clients perspectives [Master Thesis]. In Technische Universiteit, Eindhoven (Issue december). Technische Universiteit, Eindhoven.

Irwin, T., & World Bank. (2003). Public money for private infrastructure: Deciding when to offer guarantees, output-based subsidies, and other fiscal support. World Bank. https://books.google.co.id/books?id=S26hNmkCrCYC

Ke, Y., Wang, S. Q., Chan, A. P. C., & Lam, P. T. I. (2010). Preferred risk allocation in China’s public-private partnership (PPP) projects. International Journal of Project Management, 28(5). https://doi.org/10.1016/j.ijproman.2009.08.007

Kim, K., Cho, H., & Yook, D. (2019). Financing for a sustainable PPP development: Valuation of the contractual rights under exercise conditions for an urban railway PPP Project in Korea. Sustainability (Switzerland), 11(6). https://doi.org/10.3390/su11061573

Kokkaew, N., & Chiara, N. (2010). Modelling completion risk using stochastic critical path-envelope method: A BOT highway project application. Construction Management and Economics, 28(12). https://doi.org/10.1080/01446193.2010.521755

Kumar, L., Jindal, A., & Velaga, N. R. (2018). Financial risk assessment and modelling of PPP based Indian highway infrastructure projects. Transport Policy, 62. https://doi.org/10.1016/j.tranpol.2017.03.010

Lam, K. C., & Chow, W. S. (1999). The significance of financial risks in BOT procurement. Building Research and Information, 27(2). https://doi.org/10.1080/096132199369552

Maharani, Y., Palupie, R., & Yuniarto, H. A. (2016). Alokasi Risiko Proyek Infrastruktur Dengan Skema Kerjasama Pemerintah dan Badan Usaha (KPBU)?: Suatu Tinjauan Literatur. UGM Press.

Ng, A., & Loosemore, M. (2007). Risk allocation in the private provision of public infrastructure. International Journal of Project Management, 25(1). https://doi.org/10.1016/j.ijproman.2006.06.005

Nurhayati, E., & Wahyuni, E. T. (2020). Tinjauan Topik-Topik Penelitian Dan Kajian Tentang Proyek Jalan Tol Di Indonesia Dengan Skema Kerjasama Pemerintah Badan Usaha (KPBU). Jurnal Sosek Pekerjaan Umum, 12(April 2020).

Purwanto, E. A. (2023). Siapa yang Membiayai Proyek pada Skema KPBU? KPBU Kemenkeu.

Remi, F. F. (2017). KAJIAN FAKTOR PENYEBAB COST OVERRUN PADA PROYEK KONSTRUKSI GEDUNG. Jurnal Teknik Mesin, 6(2). https://doi.org/10.22441/jtm.v6i2.1187

Santoso, D. S., Joewono, T. B., Wibowo, A., Sinaga, H. P. A., & Santosa, W. (2012). Public-private partnerships for tollway construction and operation: Risk assessment and allocation from the perspective of investors. Journal of Construction in Developing Countries, 17(2).

Siemiatycki, M., & Friedman, J. (2012). The Trade-Offs of Transferring Demand Risk on Urban Transit Public-Private Partnerships. Public Works Management and Policy, 17(3). https://doi.org/10.1177/1087724X12436993

Sutantiningrum, K. H., & Utami, S. R. L. (2019). Strategi mitigasi risiko proyek kpbu pembangunan spam regional: studi kasus spam regional Wosusokas Provinsi Jawa Tengah. Prosiding Seminar Nasional Unimus.

Wibowo, A. (2016). Perkembangan Terkini Dalam Pembiayaan Infrastruktur yang Melibatkan Partisipasi Badan Usaha. Konferensi Nasional Teknik Sipil.

Xenidis, Y., & Angelides, D. (2005). The financial risks in build-operate-transfer projects. Construction Management and Economics, 23(4). https://doi.org/10.1080/01446190500041552

Yun, S., Han, S. H., Kim, H., & Ho Ock, J. (2009). Capital structure optimization for build-operate- transfer (BOT) projects using a stochastic and multi-objective approach. Canadian Journal of Civil Engineering, 36(5). https://doi.org/10.1139/L08-134

Zhu, L., & Chua, D. K. H. (2018). Identifying critical bankability criteria for PPP projects: The case of China. Advances in Civil Engineering, 2018. https://doi.org/10.1155/2018/7860717